client login button for construction updates
Each custom home builder client can access up-to-date plans, construction photos and documents for their project. This is a FREE service provided to all
Matustik Builders
clients and can be accessed with any Internet connection.

Customer Testimonials

"John is one of my trusted referrals. John’s customer service, attention to detail and experience are some of the many qualities he brings to every meeting and relationship; John is on 100% of the time regardless of how busy he is.

You are always the top priority as one of his clients. I have enjoyed working with him on our Lake Properties as much as my clients."
Michalene Melges

Matustik Custom Dream HomesBuilders - Dream, Design & Build
We will build your Dream Home, On Time, On Budget, Guaranteed!

At Matustik Builders,  we have a step-by-step plan that will take each customer from the first construction phase to the final inspection where they are given the keys to their new home.

  • Preconstruction

    Content on this page requires a newer version of Adobe Flash Player.

    Get Adobe Flash player

    At the preconstruction meeting, you are invited to sit down with your sales person, superintendent and possibly a customer service representative for a final review of your dream home package. Together, you'll verify the placement of the house, review the blueprints, and find out what to expect during the building process. When city and county permits are cleared, construction can begin.
  • Foundation
    The first step to building a quality home is laying the foundation. Matustik Builders analyze soil conditions, ground integrity, government requirements, wind patterns and home size to ensure that a quality structural system is built for your home. We use post-tension engineering to help ensure the stability and integrity of each foundation.

  • Lumber Drop & Framing
    The frame is the skeleton of your home. Frames can be wooden, cement block or other materials based on specific conditions. The framing stage usually takes one to four weeks, and consists of the following:
    • The walls start going up on the first day of frame start, as the first floor is constructed.
    • Once the first-floor walls are up, work starts on the second-floor system (if applicable), using engineered floor joists.
    • Roof trusses arrive at the homesite just as work is finished on the second floor.
    • Once the roof trusses are in place, the entire roof is installed.

  • Plumbing & Electrical
    During this one-to-three week phase, air conditioning, heating, ventilation, plumbing and electrical wiring are installed.
    • Once the roof is installed, the exterior detail work begins, including trim, windows and doors.
    • HVAC (heating, ventilation, air conditioning) and plumbing systems are “roughed-in” as exterior trim is completed.
    • The electrical system is “roughed-in” during two days.
    • Exterior trim is painted as activity continues inside.
    • Roofing and the installation of phone, cable and other electrical systems occur simultaneously.

  • Drywall
    Drywall is stocked in the home while insulation, gas meters and permanent power connections are installed. It frequently takes two full days to hang interior drywall. Next, drywall taping and finishing are scheduled to take five days and blown insulation is installed. After the interior walls are touched up, the walls and ceiling are textured.

  • Trim & Finish Detail
    Now the fun really starts. During this two-week phase, you will begin to recognize the home you designed and imagine the future you'll create.
    • Walls are prime-painted and prepared for final finish, while interior trim, cabinets, counters and sinks are installed.
    • Completion of electrical systems occurs as wire shelving, bath accessories and mirrors are installed.
    • Ceramic tile and any vinyl and/or wood flooring are installed.
    • Any necessary grading occurs outside (weather permitting) as hardware fixtures, shoe molding and carpeting are installed.
    • Final touches (gutters, mailboxes, garage door openers, etc.) are completed as the entire home is cleaned.

  • Final Third Party Inspection
    Workers wait until this final week to install the flooring, in the interest of protecting your carpets and hardwood from boots, nails and dust. Any minor adjustments take place now.
    • Appliances are installed.
    • Door and window screens are installed.
    • Carpeting is installed.
    • Various final inspections (bank, city, etc.), garage cleaning and paint touch-ups take place.

  • Homeowner Orientation
    The Homeowner Orientation provides buyers with the opportunity to become acquainted with their new home prior to moving in. During the orientation, a Matustik Builders Customer Service Representative provides a thorough demonstration of the completed home (e.g., mechanical components, appliances, etc.) and reviews items covered by the warranty.

Call for your free consultation today!